Gray & Osborne, Inc., Consulting Engineers

TABLE 8-2

6-YEAR CAPITAL IMPROVEMENT SUMMARY

  ESTIMATED YEAR OF COST TOTAL
IMPROVEMENT 1999 2000 2001 2002 2003 2004 COST (1) (2)
T-1  Interim Treatment Plant Expansion $490,000 $2,570,000 $809,000       $3,869,000
L-1 LS No. 3 $18,000           $18,000
L-2 LS No. 4 $18,000           $18,000
L-4 LS No. 6 $29,000           $29,000
L-5 LS No. 8 $343,000           $343,000
F-1 LS No. 5 Force Main Replacement     $705,000       $705,000
F-3 LS No. 8 Force Main Extension (Davies) $651,000           $651,000
O-2 Facility Plan $140,000           $140,000
O-3 I/I Monitoring & Reduction Prog.  $25,000 $25,000 $24,000       $75,000
G-6 91st Ave. Upgrades     $470,000       $470,000
G-1 Lundeen Parkway/Vernon Road       $1,245,000     $1,245,000
F-2 SW Interceptor Tightline         $735,000   $735,000
G-4 SW Interceptor (Hewitt - SR204)           $2,091,000 $2,091,000
O-1 Comprehensive Sewer Plan         $85,000   $85,000
Total: $1,714,000 $2,595,000 $2,009,000 $1,245,000 $820,000 $2,091,000 $10,474,000

Notes:
(1) ENR Index = (August 1998)
(2) Includes Tax, 20% Contingency, and 25% Engineering and Administrative Costs